SRL at Cheltenham: digging has started, but our station isn't signed
The tunnel boring machines are underground, but not at our end yet. The Auditor-General says Cheltenham's station contract is a year late and not fully funded.

The Suburban Rail Loop is the biggest thing to happen to Cheltenham in a generation, and the hoardings are up from Bay Road to Kingston Road. The official line and the audited reality don't quite match. Here's where SRL East really stands for our end of the line, based only on what the project and the state Auditor-General have published.
What's coming
SRL East is 26 km of twin tunnels from Cheltenham to Box Hill, with six underground stations: Cheltenham, Clayton, Monash, Glen Waverley, Burwood and Box Hill. Passenger trains are due in 2035 (Big Build).
Cheltenham station will be built under part of Sir William Fry Reserve in Highett, with an entrance facing Bay Road and a link to the existing Southland station on the Frankston line. The platform will be about 17 m down. The project expects around 8,000 passengers a day, about 2,700 of them changing to or from the Frankston line. A walking and cycling overpass is planned for Bay Road, and the project says the reserve land it takes will be replaced with open space nearby (fact sheet).
Tunnelling: started, but not here
Three tunnel boring machines (TBMs) were underground by late October. One, TBM Aayushi, launched from Clarinda and is heading north towards Glen Waverley. A fourth, Belinda, is being assembled at Clarinda. Since September they've dug 138 m between them (Big Build, 26 Oct).
The tunnels to Cheltenham come next year, when more TBMs launch from Heatherton (tunnelling works). The good news for Highett and Cheltenham is that the soil dug from under us will come up at Heatherton, not at the station site.
Heatherton: the real construction zone
The SRL train stabling yard is going in at 91–185 Kingston Road, Heatherton. Trains will be parked, cleaned and maintained there: 13 at opening, up to 30 in the long run. Crews are moving underground services, building the eastern and western tunnel entrances and putting up a facility to power the TBMs (train stabling). Monthly works notices for Cheltenham and Heatherton are on the Big Build notices page.
The catch: our station contract isn't signed
This is the part the glossy updates skip. In August the Victorian Auditor-General (VAGO) reported that procurement of the two station packages was running about a year late.
The southern package, WPE, covers building and fitting out the stations at Cheltenham, Clayton and Monash, and digging the Cheltenham station box. It was targeting a contract award in May 2027 and practical completion in April 2034 (VAGO Appendix F).
VAGO also found the state didn't yet have enough approved funding to sign that contract. It judged the project more likely than not to exceed its stated cost of up to $34.5 billion, and called the 2035 opening target "at risk" (VAGO report). The project authority disagrees: according to the same report, it is forecasting delivery on budget and on time.
Why it matters: the tunnels can arrive on schedule, but without a signed and funded station contract, Cheltenham's station is the piece still at risk. Whoever forms government after Saturday's election inherits that decision.
Living with it this summer
- Near Southland and Sir William Fry Reserve: ongoing site works, with occasional lane or footpath changes. Check the monthly Cheltenham notice.
- Kingston Road, Heatherton: day and night works, with some overnight road closures flagged through 2026.
- Questions or complaints: call the project line on 1800 105 105.
We'll keep watching the Cheltenham station contract and every new works notice for 3192.
Sources
- bigbuild.vic.gov.au
- bigbuild.vic.gov.au
- bigbuild.vic.gov.au
- bigbuild.vic.gov.au
- bigbuild.vic.gov.au
- audit.vic.gov.au
- audit.vic.gov.au
We've done our best to get everything right from locally available sources, but please check with the venues to confirm before you head out. Times and details can change. Spotted a mistake? Tell us and we'll fix it.